Wiring office cubicles with Cat 6 in Draper, Utah

Cat 6 cable passing through adjoining cubicle frames in Draper, Utah

In Draper, Utah, 1GC ran Cat 6 through a bank of office cubicles, terminated the workstation jacks, installed the faceplates, and tested the cabling. Once the partitions were closed, someone sitting at a desk would see just a numbered data jack beside the power outlets. The installation photos show the route behind it.

Following the cable through the partitions

The open frames gave our crew access to the lower channel between workstations. We routed the bundle around the corner and brought individual cables out through the openings for the workstation plates.

White cable emerging from the faceplate opening at the base of a Draper workstation partition
The cable reaches the workstation through the opening for the faceplate.
Open cubicle frame with cables along the lower channel
The open panel exposes the path between workstations.

Terminating, labeling, and testing the jacks

At the workstation, we terminated the cable on a jack, fitted the faceplate, and tested the connection. A label such as J-3 gives the office a specific outlet to identify when a desk moves or a technician needs to trace the line.

Loose data cable at a cubicle outlet strip
The cable end at the workstation before termination.
Finished data jack labeled J-3 beside a power outlet
A finished workstation connection with its jack and faceplate installed.

Explore our structured cabling services, see other Wasatch Front projects, or request a site survey.

Structured cabling and OS2 fiber installation in Sandy, Utah

Blue and orange patch leads at the Sandy, Utah project network rack

In Sandy, Utah, our crew pulled roughly ten boxes of Cat 6 cable for a structured cabling and OS2 single-mode fiber installation. The finished wall plates show only the last few inches of that work. The installation photos show where the rest of the cable went.

Pulling Cat 6 through the office

With the ceiling open, we pulled the copper runs overhead between the outlet locations and the network rack. At the room end, a single faceplate could bring six runs together. At the rack, the cables from those outlets came together in bundles before we terminated them on the patch panels. The two views below show the same stage of work from opposite ends of the route.

Bundles of white Cat 6 cable following the open office ceiling in Sandy
Above the office, the open ceiling shows the path the crew used for the cable pull.
Incoming cable bundles hanging in front of the network rack during installation
At the network rack, the incoming runs are visible before final patching.

From open framing to labeled data outlets

Before the wall was closed, the metal studs, conduit and outlet box were accessible. At the room end, the crew terminated the cables on individual jacks. One finished six-port plate carries the label J1–6. That gives someone reporting a connection problem a specific outlet to identify.

Conduit entering a metal outlet box on an exposed stud
The outlet location during rough-in.
White faceplate labeled J1–6 with six blue data jacks
Six data connections share one labeled faceplate.

Copper patching and the fiber uplink

In the rack, patch panels bring the copper runs together. Short patch cords link those terminations to switch ports. The yellow fiber lead connects at the switch uplink. A separate field photo shows visible light at a fiber connection during a check of the optical path.

Yellow fiber lead plugged into a rack-mounted switch uplink
The fiber connection at the switch.
Fiber test instrument beside an illuminated fiber lead
Checking the fiber path during the Sandy installation.
Blue patch leads connecting switches and panels as the Sandy rack takes shape
The rack during patching.
Full-height view of the finished Sandy network rack with copper patch leads and yellow fiber
The finished rack, with the copper and fiber connections in place.

Explore our structured cabling and fiber installation services, see more Wasatch Front projects, or request a site survey.

Connecting the Gateway Pines buildings with OS2 fiber in Pleasant Grove, Utah

Aerial view of the two Gateway Pines buildings in Pleasant Grove, Utah, with mountains beyond.

At Gateway Pines in Pleasant Grove, Utah, a carrier serving a new tenant needs a way to reach that tenant’s suite. 1GC connected the two buildings with OS2 single-mode fiber and ran fiber to the network closet in every suite. We built the route with conduit, roughly 700 feet of orange corrugated innerduct, and two equipment racks.

Building the pathway between buildings

The route had two layers. The larger conduit formed the passage between buildings. Inside it, corrugated innerduct gave the OS2 fiber its own protected channel. The flexible tubing arrived on a spool so the crew could feed it into the route from an access point. The approximately 700-foot figure describes the innerduct we installed across the job.

Crew beside a spool of orange corrugated innerduct
At the open handhole, the crew fed orange tubing from a spool into the conduit.
Orange innerduct laid out along the building walkway
A length of innerduct laid out beside the building shows how the flexible tubing handles changes in direction.

Inside the handhole

The handhole is an access box in the ground. With its cover lifted, the conduit opening and the smaller orange ducts are visible together. From the surface, the crew could reach this junction while working on the pathway. Once the cover is back in place, very little of this part of the installation is visible.

Two crew members working at the open handhole
The crew worked at the handhole opening with the innerduct within reach.
Orange innerduct emerging from gray conduit inside the handhole
Looking down into the box, the orange tubing is visible at the mouth of the gray conduit.

Bringing the pathway indoors

At the building entrance, the work shifted from feeding duct outside to bringing it up the interior wall. In the first photo below, a technician works at floor level. In the next, the orange bends are visible below a wall-mounted rack. Together the views show the transition that a finished rack photograph alone would miss.

Technician handling orange innerduct at the interior wall
Working the innerduct at the building entrance.
Orange innerduct and gray conduit below a wall-mounted rack
The exposed bends show where the fiber pathway meets the equipment location.

Two racks and the fiber connections

A carrier can install its equipment in a rack and patch directly to the fiber serving an individual suite. At the far end, the fiber reaches the suite’s intermediate distribution frame (IDF), the location where the tenant’s network connects. This gives the carrier an existing path to the customer when it is time to turn up service.

Across the two panels, the crew installed approximately 36 LC connectors, with about 24 on one panel and 12 on the other. The close-up below shows the patch connections a technician works with when connecting a suite.

Finished wall-mounted rack with an LC fiber panel behind the glass and orange innerduct below
The finished Gateway Pines rack has room for carrier equipment above the LC patch panel. Orange innerduct rises from the conduit below.
Fiber leads routed across a panel with blue ports
The fiber panel brings individual connections together at the rack.

Planning a connection between buildings? Explore our structured cabling and fiber services, see more Wasatch Front installations, or request a site survey.

Extending a warehouse fiber circuit in West Valley City, Utah

Scissor lift raised beside the exterior wall of the West Valley City warehouse

At a warehouse in West Valley City, Utah, 1GC extended a fiber circuit from the carrier’s handoff to the equipment it needed to serve. The job combined three kinds of work: reaching the cable route, splicing the fiber, and installing the equipment at the far end.

Reaching the route inside and outside

The carrier handoff, sometimes called the demarc, is where the provider delivers the circuit. A warehouse can have plenty of space between that point and the equipment that needs the connection. Here, the crew used a scissor lift alongside the exterior wall and worked overhead inside the warehouse. The aisle view shows the cable laid out between rows of shelving.

Raised lift along exterior wall
The raised platform gave the crew access to the upper exterior wall.
Indoor lift beneath warehouse ceiling
Inside the warehouse, the lift reached the exposed ceiling above the shelving.
Cable laid out in warehouse aisle
Cable laid out along the warehouse aisle during installation.
Wall-mounted network equipment and cable pathways at the West Valley City warehouse
At the network closet, the cable pathways reach the wall-mounted equipment.
A technician runs outdoor fiber from the warehouse network closet to the carrier handoff.

Splicing the fiber and connecting the equipment

Extending the circuit required joining the optical fibers. A fusion splicer aligns the prepared fiber ends and joins them to form a continuous optical path. At the equipment end, patch leads connect that path to the network hardware. These two close-ups show the splice work and the connections a technician can access afterward.

Splicer screen and controls indoors
The fusion splicer’s display and controls during the West Valley City job.
Network equipment with fiber patch leads
Fiber patch leads connected to the installed network equipment.

For a similar project, start with the location of the carrier handoff and the room where the circuit needs to end. Explore our structured cabling and fiber installation services, see other Wasatch Front projects, or request a site survey.