At a warehouse in West Valley City, Utah, 1GC extended a fiber circuit from the carrier’s handoff to the equipment it needed to serve. The job combined three kinds of work: reaching the cable route, splicing the fiber, and installing the equipment at the far end.
Reaching the route inside and outside
The carrier handoff, sometimes called the demarc, is where the provider delivers the circuit. A warehouse can have plenty of space between that point and the equipment that needs the connection. Here, the crew used a scissor lift alongside the exterior wall and worked overhead inside the warehouse. The aisle view shows the cable laid out between rows of shelving.




Splicing the fiber and connecting the equipment
Extending the circuit required joining the optical fibers. A fusion splicer aligns the prepared fiber ends and joins them to form a continuous optical path. At the equipment end, patch leads connect that path to the network hardware. These two close-ups show the splice work and the connections a technician can access afterward.


For a similar project, start with the location of the carrier handoff and the room where the circuit needs to end. Explore our structured cabling and fiber installation services, see other Wasatch Front projects, or request a site survey.
No comment yet, add your voice below!